Construction of the Barka V desalination plant has been completed, marking the latest contractual milestone for GS Inima. The plant has completed all necessary acceptance tests, nine days ahead of schedule in the contractual schedule. With this...
Nearly 60 million euros in investments are planned over the 30 years of the contract. The city will go from 25% treated wastewater to 90% sewage. Spain, August 16, 2024. The consortium GS Inima and Traçado Construções e...